Commission method of the primary helium circulator of HTGR under variable resistance condition
-
摘要: 高温气冷堆主氦风机调试期间,由于一回路阻力低于设计工况,因而主氦风机无法完成全转速范围性能测试。基于主氦风机的理论特性与相似原理开发主氦风机不同阻力工况调试参数的推算方法。结合主氦风机单体试验工况点,准确推算主氦风机冷态与热态性能试验的工况点参数,并指导完成高温气冷堆主氦风机全转速、满功率性能测试。通过对主氦风机调试与出厂试验结果的对比分析,验证本推算方法的可行性,并给出空气介质与氦气介质工况转换的修正因子。通过主氦风机调试与运行数据的对比分析,可以看出本文提供的主氦风机调试工况具有足够的包络性,能够覆盖高温气冷堆运行期间主氦风机的所有运行工况,证明了本文提供的变阻力工况主氦风机调试方法满足高温气冷堆主氦风机性能验证需求,可用于指导后续高温气冷堆的主氦风机调试工作。Abstract: During the commissioning of the primary helium circulator of the high-temperature gas-cooled reactor (HTGR), it could not complete the performance test of the full speed range, because the resistance of the primary loop was lower than the design condition. Based on the theoretical characteristics of the primary helium circulator and similar principles, a method for calculating the commission parameters of the primary helium circulator under different resistance conditions was developed. Combined with the monomeric test operating points of the primary helium circulator, the method was used to accurately calculated the operating point parameters of the cold and hot performance tests of the primary helium circulator, and guide the completion of the full speed and full power performance tests of the primary helium circulator in HTGR. By comparing and analyzing the commission and factory test results of the primary helium circulator, the feasibility of this calculation method is verified, and correction factors for the conversion of working conditions between air medium and helium medium is provided. Through comparing and analyzing the commission and operation data of the primary helium circulator, it can be seen that the commission conditions provided in this article have sufficient enveloping ability, which can cover all operating conditions of the primary helium circulator during the operation of HTGR. This proves that the variable resistance condition commission method of the primary helium circulator meets the performance verification requirements of HTGR, and it can be used to guide the primary helium circulator commission of subsequent HTGRs.
-
表 1 主氦风机的主要参数[3]
Table 1. Main parameters of primary helium circulator
working fluid pressure/MPa flow rate/(kg/s) pressure rise/kPa rated speed/(r/min) rated electrical power/kW helium 7 96 200 4000 4500 表 2 主氦风机试验介质压力换算
Table 2. Conversion of test pressure of primary helium circulator
test working fluid temperature/℃ pressure/MPa power*/kW density/(kg/m3) monomeric test air 19.3 0.10 1019.1 1.19 cold test air 25.0 0.45 4500.0 5.27 hot test helium 250.0 5.73 4500.0 5.27 *: $ {n}_{\max} $ is equal to 4000 r/min 表 3 不同工况下主氦风机运行情况
Table 3. Operation of primary helium circulator under different working conditions
work condition speed/(r/min) current/A voltage/V power/kW pressure rise/kPa flow rate/(kg/s) pressure/MPa inlet temperature/℃ ① 3600 523.7 5614 4218 122.2 127.3 6.9 239.9 ② 4000 516 6147 4648 145.2 116.0 5.31 235.9 ③ 3800 580 6000 4500 200 96 7.0 243 ①: primary helium circulator operation at 200 MW
②: the hot function test of primary helium circulator
③: rated parameters and some design limits for primary helium circulator -
[1] Reutler H, Lohnert G H. Advantages of going modular in HTRs[J]. Nuclear Engineering and Design, 1984, 78(2): 129-136. doi: 10.1016/0029-5493(84)90298-X [2] 曾斌, 李言瑞. 高温气冷堆如何助力“双碳”?[J]. 能源, 2022, 15(8):31-34Zeng Bin, Li Yanrui. How high-temperature gas-cooled reactors can help carbon peaking and carbon neutrality?[J]. Energy, 2022, 15(8): 31-34 [3] 邹德宝. 高温气冷堆核电站示范工程主氦风机技术概述[J]. 防爆电机, 2011, 46(4):5-7Zou Debao. Technical overview on main helium ventilator of high-temperature gas-cooled reactor nuclear power plant[J]. Explosion-Proof Electric Machine, 2011, 46(4): 5-7 [4] Gambini M, Vellini M. Turbomachinery: fundamentals, selection and preliminary design[M]. Cham: Springer, 2021: 89-107. [5] 张作义, 原鲲. 我国高温气冷堆技术及产业化发展[J]. 现代物理知识, 2018, 30(4): 3-10Zhang Zuoyi, Yuan Kun. High temperature gas cooled reactor technology and industrial development in China[J]. Modern Physics, 2018, 30(4): 8-9 [6] 周惠忠, 王捷, 汤全法. HTR-10主氦循环风机的设计、试验和运行[J]. 核动力工程, 2004, 25(1):54-58Zhou Huizhong, Wang Jie, Tang Quanfa. Design, test and operation of helium circulator for HTR-10[J]. Nuclear Power Engineering, 2004, 25(1): 54-58 [7] 彭浩然, 孙俊. 高温气冷堆堆芯球床的流动与换热分析[J]. 工程热物理学报, 2016, 37(5):1076-1083Peng Haoran, Sun Jun. Investigation of flow and heat transfer in the pebble bed of the high temperature gas-cooled reactor[J]. Journal of Engineering Thermophysics, 2016, 37(5): 1076-1083 [8] 张双宝, 李良星, 谢伟, 等. 球床式高温气冷堆堆芯三维建模及稳态热工水力分析[J]. 中国科学院大学学报, 2020, 37(2):186-191Zhang Shuangbao, Li Liangxing, Xie Wei, et al. Three-dimensional modeling of pebble bed type high temperature gas-cooled reactor core and steady-state thermal hydraulic analysis[J]. Journal of University of Chinese Academy of Sciences, 2020, 37(2): 186-191 [9] 陈卓. HTR-PM主氦风机叶轮气动性能优化研究[D]. 衡阳: 南华大学, 2020: 9-22Chen Zhuo. Study on the aerodynamic performance optimization of the impeller of the helium circulator of HTR-PM[D]. Hengyang: University of South China, 2020: 9-22 [10] 蔡兆麟, 刘华堂, 何国庚. 能源与动力装置基础[M]. 北京: 中国电力出版社, 2004: 58-90Cai Zhaolin, Liu Huatang, He Guogeng. Fundamentals of energy and power equipment[M]. Beijing: China Electric Power Press, 2004: 58-90 [11] 王捷, 周惠忠, 汤全法. HTR-10主氦风机性能试验研究[J]. 高技术通讯, 2002, 12(11):96-100Wang Jie, Zhou Huizhong, Tang Quanfa. Performance test of HTR-10 helium circulator[J]. Chinese High Technology Letters, 2002, 12(11): 96-100 [12] 王捷, 周惠忠. HTR-10一回路流道气动特性和主氦风机运行参数的研究[J]. 高技术通讯, 2003, 13(3):92-97Wang Jie, Zhou Huizhong. Study on pneumatic features of primary system and operation parameters of helium circulator for HTR-10[J]. Chinese High Technology Letters, 2003, 13(3): 92-97